Updates
October 2024
The contractor is continuing work on the sidewalk along Alameda De Las Pulgas. Please be advised the traffic delays are expected within the construction zone.
September 2024
September 2024: NTP issued on 8/29 . RK Engineering will be in the field starting September 3, 2024 to perform initial field survey and other preparation work.
Demolish and sidewalk work scheduled to start September 16, 2024. Work to start at Avy Ave and Alameda De las Pulgas. Expect delays through work zone.
Please click HERE to download the general construction notice.
July to August 2024
Pre construction meeting was held on July 18th. Construction is scheduled to begin by end of August. DPW to provide an update for the Santa Cruz Avenue and Alameda de las Pulgas Improvement Project at the San Mateo County Bicycle Pedestrian Advisory Committee (BPAC) meeting on Thursday August 15, 2024.
Information on how to attend the meeting can be found at the following link.
June 2024
Bids were received and opened on June 6, 2024. Lowest apparent bidder is RK Engineering Inc. Contract award for this Project is scheduled on June 25, 2024.
April/May, 2024
On April 16, 2024, the Department has been awarded $5.4 Million for the construction of this Project by the California Transportation Commission. The Board of Supervisors approved the Project on April 23, 2024. Project advertisement for bids started on April 25, 2024, with an anticipated bid opening date in late May/June 2024. Construction is anticipated to start in late Summer of 2024 and projected to take 12 months to complete.
March 22, 2024
California Transportation Commission (CTC) allocated grant funding to the County for the construction phase of the Project under the Active Transportation Project (ATP).
February 16, 2024
Parking Exhibit can be reviewed below which includes an updated parking space count and striping plan.
July 28, 2023
Documents from the April 2023 meeting are now online and can be reviewed below, including the public meeting Q&A, public comment cards, PowerPoint presentation, presentation video, truck turn exhibits, and design aerial plot.
Please Click HERE for the recorded Public Meeting on April 18 2023.
March 28, 2023
Notice of community meeting to be held on Tuesday April 18, 2023 at 6:30PM-8:00PM.
Please click HERE for details and to download the notice.
November 15, 2022
The 90% complete plans were recently completed and reviewed by the Department.
The attached link provides the 90% design plans, please click HERE to download.
No public comments were received via email at the 60% plans, and the County has moved onto the 90% plans.
The information being provided is for general informational purposes only and the Project Plans are not approved for construction. Any questions or comments regarding the plans can be sent to DPW_santacruzalameda@smcgov.org.
April 26, 2022
The 60% complete plans were recently completed and reviewed by the Department.
The attached link provides Project information and the 60% design plans, please click HERE to download.
The information being provided is for general informational purposes only and the Project Plans are not approved for construction. Any questions or comments regarding the plans can be sent to DPW_santacruzalameda@smcgov.org.
November 1, 2021
Preliminary Design for the Santa Cruz Avenue and Alameda de las Pulgas Improvement Project has begun.
Location
About the Project
The Santa Cruz Ave/Alameda de las Pulgas Corridor Improvement Study project will evaluate possible roadway configuration alternatives along Santa Cruz Avenue from Sand Hill Road to Alameda de las Pulgas, along Alameda de las Pulgas between Santa Cruz Avenue and Sharon Road, and Santa Cruz Avenue from Alameda de las Pulgas to Sharon Road, to determine what safety and connectivity improvements can be achieved for bicycles, pedestrians, and vehicles. The project is led by the County of San Mateo Public Works Department in collaboration with the City of Menlo Park. The County has retained a consultant, Kimley-Horn, to perform the technical analysis and identify feasible solutions.
Next Steps
The consultant gathered additional vehicle, bicycle, and pedestrian count information during the early part of May 2017 to ensure the data included school traffic. June through July 2017, the consultant will analyze this data, previous planning studies, existing conditions, and collision history to identify roadway improvement opportunities. This analysis will be used to begin developing a variety of possible improvements that could be applied to the corridor. As part of the identification of improvements, the consultant will identify the trade-offs associated with each of those improvements for all corridor users. A range of feasible improvements and their trade-offs will be presented to the public on August 28, 2017, at a community meeting. Attendees will have an opportunity to weigh in on the range of potential improvement alternatives and share their preferences for the various alternatives. During the summer of 2018, the Task Force released a questionnaire to all users of this corridor to collect these preferences. Results of the questionnaire and executive summary are listed on the link to the questionnaire and in an executive summary for information only.
This information will be used to develop a recommended corridor improvement plan. An additional community meeting will be held at the end of 2019 to review the refined proposed improvements.
Summer 2019 Pilot Project - still in place.
January 30, 2020 - public meeting to discuss potential alternatives for corridor improvements.
January 31, 2020 thru February 24, 2020 - online survey to select preferences - open to the public
Background
The Santa Cruz Ave/Alameda de las Pulgas Corridor Improvement Study was developed in response to input received at a community meeting held on January 23, 2017. The Board of Supervisors approved $78,000 in funding for this project at their regularly scheduled meeting on April 25, 2017.
The contractor/consultant was approved through a competitive bid process for on call services. Seven Traffic Engineering firms competed for the Public Works Department's on-call services contract and Kimley Horn was one of three chosen through the process. Of the three, Kimley Horn has extensive knowledge of this particular corridor through work performed in the immediate area, including Alpine Road, Page Mill Road at 280 and Sand Hill Road. They were chosen as the most logical firm to lead a study effort at this location, given their extensive knowledge of the corridor.
October 26, 2017 the Task Force began monthly meetings with DPW. The Task Force will be asked to review and evaluate conceptual plans to be included in the master plan for safety improvements in this corridor. Final results will be presented to the public for review and comment (tentatively in the Fall of 2019). Meanwhile, installation of reduced speed limits, radar feedback signs, placement of sharrows and other near term road improvement projects are currently underway.
January 30, 2020 public meeting was held at Las Lomitas School to present 4 alternative proposals for this corridor. The public is invited to take the survey on the link above. Task Force members will reconvene after the survey closes to select the preferred alternative prior to going to the Board of Supervisors for approval.
Action Item Minutes of the meetings are available for viewing below. Materials presented at the meetings are also attached. Please note that the presentations attached here are for reference and represent the views of some of the stakeholders but do not represent the views of all the Task Force members.